Latest Building Development News

4 July 2020

Levels 1 and 2 units are complete in all respects and ready for Defects inspections.

Level 3 units are 90% complete with only some minor fitout items to complete.

Plaster is 90% complete on Level 4 with tiling and joinery fitouts continuing with completion of all units now scheduled by the end of the second week in July. The Surveyor continues with his role in getting Strata Titling completed.

Electrical wiring, plumbing and air-conditioning pipework is advancing well, with lighting functional on Levels 1, 2 and 3, and wiring well underway on Level 4.

The Lift is operational and has been handed over to the builder. The Builder has been instructed that it is not to be used during construction. I have had the privilege of testing it out and I can say it is a very smooth ride. Beats climbing the stairs which I have had to do on many occasions!

Drainage work in the Carpark is complete and Carpark preparation for paving works and kerbs and channelling are continuing externally. The stormwater pits and grease trap have been installed.

The Boundary fencing on the Western and Northern boundaries is well advanced.

Getting TasWater to site to complete the water supply connection and required alterations remains a concern.

The current scheduled completion date of Stage 2 (units) has been foreshadowed by the Builder as the first week of August.

The builder has commenced work on parts of Stage 3 and works are well under way. Demolition has been completed in readiness for reinstatement works to commence in the Upper Hall and Soundy Building Laneway.

Antal Hanke – Project Manager

Carpark Preparation
Carpark Preparation
Northern Boundary Fence
Northern Boundary Fence
Western Boundary Fence
Western Boundary Fence
Carpark almost ready for bitumen sealing
Carpark almost ready for bitumen sealing

Earlier updates available here >>>